METHOD STATEMENT FOR PILE CAP, TIE BEAM AND PERIMETER WALL CONCRETING


TABLE OF CONTENTS

1.0        INTRODUCTION                                                                 
2.0 REFERENCES                                                                
3.0 RESOURCES                                                                 
4.0 FORM WORK                      
5.0 RAINFORCEMENT WORK   
6.0 CONCRETE WORK                                                                                    
7.0 RESPONSIBILITIES                                                        
8.0 QUALITY ASSURANCE / INSPECTIONS AND TESTING                          
9.0 SITE ARRANGEMENTS                    
10.0 SAFETY PLAN                                                      
                                                           
METHOD STATEMENT FOR PILE CAP AND TIE BEAM CONCRETING
1.0       INTRODUCTION

·         WPC Office complex is a sixteen storied building with total floor area of about 40,000sq.m including basement parking area, eleven no’s of office floors and council chamber at the 13thfloor level. It has been designed for bored pile and bulking pile cap foundations as well. This Method statement describes the way of doing concrete casting for Pile caps, Tie beams and Perimeter walls. Quality Assurance and Quality controlling plan also enclosed in the method statement.

2.0       REFERENCES

  • Structural Construction Drawings
  • Waterproofing Method statement   - to be submit separately
  • Termite treatment Method statement - to be submit separately
  • Inspection sheet for structural work
  • Form work method statement
  • Trial Mix Reports/ Admixture Reports

3.0       RESOURCES

3.1. Material
1.   Cement Blocks (200 mm thk.  Solid )
2.   Timber – 50 x 50 , 100 x 50 mm
3.   12 mm thk. Ply wood sheets
4.   Form ties and pre cones
5.   GI Pipes / acro jacks – For support
6.   Ordinary Portland Cement
7.   Aggregates
8.   Sand
9.   Water
10.        Admixtures
11.        Water Bars
12.        Ready mix Concrete ( as per approved mix design )
The mix proportions are designed by mix design and verified by Trial mix and trial workability tests.



1.    Batching plants
2.   Truck Mixers
3.   Stationary Concrete Pump with Lines/ Pump Cars
4.   Concrete Distributor
5.   Shovel/Mammoty
6.   Porker/Shutter Vibrator
7.   Level Bar
8.   Level Machine with  staff
9.   Concrete Chute
10.        Tower Crane with Bucket
11.        Mason Trowel
12.        Wooden Float
13.        Plumb bob
14.        Water pressure gun m/c
15.        wire brush


3.3. Man Power
1.  In charge Engineer (Structural) – 01 no
2. Concrete In charge Engineer – 01 no
3. Assistant Engineer – 01 no
4. Construction Supervisor – 01 no
5. Survey Helper- 01 no
6. Concrete Forman – 01 no
7. Masons – according to requirement on that time
8. Skilled Workers - according to requirement on that time
9. Unskilled Workers- according to requirement on that time
10. Standby Carpenter - according to requirement on that time
11. Standby MEP Service Workers -according to requirement on that time
12. Machine Operators - according to requirement on that time
13 .QA/QC Engineer – 01 no
                                                                          

4.0 Form Work


This is a major activity which bare the weight of concrete till it get the required strength. So it is essential to take care of the correct methodology for fixing and supporting.

4.1 Type of form work


·         Sides of Pile caps  
·         Sides of Beams
·         Perimeter Walls

4.2 Preparation of formwork

Pile cap and  tie beam area floor leveled and compacted as per the correct required  levels . after that screed concrete lay accordingly to requirement .

4.2.1 Formwork Arrangement –Pile caps and Tie beams  


  • Before start the pile cap setting out we get approval for as built drawing for pile layout from consultant.
  • After laying screed concrete  we are doing the setting out work  for pile caps and tie beams . Then start the pile caps and tie beams  form work
  • 200 mm thk. Solid cement blocks used as a form work for pile caps and tie beams
  • Verticality of block walls  will be checked using plumbs
  • Sketch 1 and Sketch 2 is attached for reference. Its show supporting system for pile caps and  tie beams
  • Shoring work beams, wales and ties details and design calculations are submit with shoring and dewatering method statement

4.2.2 Formwork Arrangement – Perimeter walls

  • Marine plywood (12mm thick) will be used for smooth finishing surfaces
  • 50 mm height kickers will be casted after locating position
  • Verticality of the mould will be checked using plumbs on each surface  
  • Sketch 3 is shown supporting system for walls


4.3 Construction Joints

Tie beams may be temporally stopped keeping continuation further and called construction joint. The way is depend upon structural definition keys will be provided as required on specifications and Pile cap construction joint shows in sketch 1and sketch 2 .Tie beam vertical construction joint keep 1/3 or 2/3 of  concrete beam span .

4.4 Cleaning of formwork

  • Surfaces will be well cleaned of all dirt with compressor or water pressure m/c

4.5 Removal of Formwork


All formwork should be removed without damage on concrete. The form of supports would not be struck until the concrete has reached the sufficient strength. Form work may be removed after the time as shown in the following,
Cement Block form work keep as it is after done the concrete

Form work removing done according to Table 2.2 in specification if we concrete without admixtures  or refer table 5.3 at ICTAD  Building works volume 1 .

4.6 Stacking of removed formwork

  • Removed panels will be stored at safe covered place
  • All panels will be installed vertically

4.8 Check List
  • Marking lines
  • Alignment of vertical form work
  • Levels of horizontal formwork
  • Supports
  • Dimensions
  • Joints of panels
  • Cleaning of form work

4.9 Quality Controlled measures

Engineer or Ass. Engineer re check marked lines. First block wall lying is check by Engineer or related officer. After finished the block work again verticality check. In between time period supervisor will be check verticality of form work and neatness of block wall. After finished the form work supporting systems and dimensions are recheck before start the re bar work.


5.0 Re bar Work

  • Mill reports and test reports for steel will be submitted to the consultant before execution of work
  • Re bar schedules will be prepared by an Engineer  
  • Cutting and bending will be done at site or bar bending yard accordingly bar schedule.
  • All laps, joints and anchorage will be kept to the standard given in drawing by consultant

5.1 Equipment’s

  • Bar bending machine
  • Bar cutting machine
  • Chop saw m/c

5.2 Reinforcement steel placing

  • All steel bars will be cleaned before placing
  • Cover blocks will be used to maintain the adequate cover to reinforcement
  • Chairs or Stools will be used to maintain the gap between top and bottom bars

5.3 Cover to reinforcement
          Cover to reinforcement will be follow as per structural drawing and related site instructions .

Minimum lap length as specified by consultant


5.5 Check List of Re bar

  • Steel sizes, spacing and position
  • Steel tying and binding
  • Lap length, anchorage length
  • Covering
  • Chairs or stools between top and bottom net
  • Cleanliness,


If any MEP  work related to pile cap , place and confirm prior to concrete works .


6.0 CONCRETE WORK

6.1 Materials
  • All concrete grades will be used as specified in drawings and Consultants

6.2 Concrete Used
  • Site Mixed ( get prior approval from Consultant )
Using concrete mixtures done by manually at site for G15  
  • Batching Plant Mixed
Concrete batching plants Mix Designs approval gets from consultant


6.3 Transportation of concrete
  • Concrete will be transported to the site by truck mixers from batching plant
  • Site mixed concrete done by at site for G15 ( using gage boxes and necessary inspection to check quality )

6.4 Placement of Concrete

  • Consultant will be informed at least 12 hours before approval required
  • If needed we used a pump car or Tower crane to pump concrete.
  • As level increases, permanent pipe lines will be installed to pump concrete
  • After the approval of consultant for reinforcement and form work, concreting will be done with all necessary equipment
  •  Chute will be used where required keeping slopes not to cause segregation
  • Poker vibrators shall be used to compact the concrete well

6.5 Leveling of Concrete
  • Height gauges will be used to maintain the correct levels
  • Concrete finish level will be marked at Column reinforcement to control the pouring on pile caps
  • Concrete finish level will be checked after concreting using leveling instrument
  • If necessary string is used to checked level of concrete

6.6 Pile Cap Concreting
  • Dust and debris, which exist inside the formwork, shall be blowered and cleaned well, prior to commence the concreting. Cavities if there are any, shall be sealed to avoid grout leakages. Pile cap shall be concreted by using the mobile or stationery concrete pump and distributors. Concrete shall be poured in to the pile cap.
  • Proper compaction shall be done by using poker vibrators. Level of the pile cap and the surface finish shall be maintained while doing the concreting. A careful attention shall be paid to ensure whether the conduits and other service lines are not damaged (if embedded); and if there are damages in service lines, it shall be informed to the relevant sub-contractor. If somewhere concrete not segregation in significant that concrete part remove .

6.7       Large scaled Pile Cap Concreting
The large scaled element, which the depth is higher than 1000mm,shall be concreted strip wise, as shown in the follow  and the thickness of concrete layers shall not be exceeded 1000mm. By doing this way, it can be laid the concrete, over the previously concreted layer before it is getting set.



 6.8 Compaction of concrete
After pouring one layer, the compaction of about 25sec to 30sec, shall be done by inserting vibrator based on the marks. The vibrator needle should not disturb previously concreted layers. Vibrator inserted in 1m intervals of above intervals .



6.9       Testing related to the Concrete work


  • Slump will be checked for each truck mixer and record with consultant representative
  • 150mmx150mmx150mm test cubes will be produced for compressive strength checks for 7 days and 28 days
  • Test cubes will be checked in NBRO or related Lab  



6.10 Curing of concrete

  • Curing shall be started as soon as possible and practical after placement of concrete
  • The concrete shall be covered with a layer of sand  and kept constantly wet for a period of 7 days


6.11 Green Removing

Removing of the grout, wire brushing of the construction joints or cleaning with water pressure gun shall be carried out within the concrete is in the fresh state.


6.13 Check List


  • Form work
  • Reinforcement
  • Supports
  • Manpower
  • Machinery and equipment arrangement
  • Sample testing




7.0. RESPONSIBILITIES

Position
Responsibility
 Engineer in charge (structural)
1.   Get approved for Concreting (i.e. for  R/F, F/W and for Services)
2.   Cleaning of debris in the form work.
3.   Sealing the joints of formwork to avoid the grout leaks.
4.   Arranging all infrastructures for Concreting.
5.   Curing of Concreted elements.
Concrete In charge Engineer
1.   Estimating the required Concrete volume and order from the batching plant.
2.   Testing and Sampling the Concrete.
3.   Keeping records of concreting.
4.   Handling the traffic of the Concrete truck mixers.
5.   Quality controlling of Concreting.
Assistant Engineer
Assist to the Tower Incharge.
Construction Supervisor
1.   Assist to the Concrete Incharge.
2.   Handling the Concrete gang.
Concrete Forman
Handling the Concrete gang.
Survey Helper
Maintaining the verticality and required levels of the concrete elements.
Admin Officer
Providing the welfare facilities for Concreting staff and for workers.
Safety Officer
Marinating Safety and Health in the working area.







8.0. QUALITY ASSURANCE / INSPECTIONS AND TESTING 

8.1               Material

Slump Value     :        Specified slump value +/- 25 mm
Grades of Concrete: 30N/mm2 for Piles
                                 40N/mm2 for Pile caps 




8.2 Concrete Sampling & Testing Plan

Samples shall be taken for cube crushing test as follow by specification or consultant instruction:



8.3 Inspection for Construction

All kinds of inspection for construction shall be carried out by the site Engineers along with Engineers representative and QAQC Engineer of SANKEN as per the standards and specifications.

However, prior information shall be given to Consultant representative at site to proceed necessary checking’s periodically & make final comments.

Inspection shall be carried out while progressing of the work & approval shall be granted without affecting to the progress of the work.
Following Forms are used for the above quality maintaining works.

1)   Quality Check Lists and Approval Sheets For Structural Work
2)   MEP Inspection sheets if available




9.0     SITE ARRANGEMENT

Site Infrastructure Arrangement plan is attached as annexure.

10.0                 SAFETY  PLAN

·         All the dangerous areas must be barricaded
·         Safe flat forms for working at higher levels shall be provided.
·         Safety Guard rails shall be provided at the perimeter run.
·         All the electrical wires and sockets such a way that must be covered to safety regulations
·         Very good site illumination will be provided, if concrete pouring continues to the night time.     
·         Water pumps must be ready at any time for immediate use.
·         First aid facilities and vehicles for emergency cases shall be available at site.
Refer the Sanken Lanka Safety Manual for other safety precaution and regulations.