METHOD
STATEMENT FOR SKIM COAT
1.
Introduction
2.
Option 1 - Applying procedure for Hega wall putty
3. Option 2: Applying procedure for Apex Skim Coat
3. Option 2: Applying procedure for Apex Skim Coat
4.
Responsibilities
5.
Inspection for Construction
6. Safety Plan
6. Safety Plan
1.0 Introduction
We Selected the following Two Suppliers for Supply Skim Coat due to excessive
Q’ty of the project.
1.
Snowplow
Industries (Pvt) Ltd – Hega Wall Putty
2.
Dblend Coatings
(Pvt) Ltd – Apex Skim Coat
This method statement gives a step by step procedure for Applying Skim
Coat for the walls.
Option 1 & Option 2 describe applying procedure for a skim coat from
above two suppliers.
But we shall only use one product to complete a skim coat for one floor.
2.0 Option
1: Applying procedure for Hega wall putty
Hega Wall putty can be used on concrete, rendered wall,
hollow block, precast walls, concrete ceilings, calcium silicate bricks &
aerated lightweight blocks.
2.1 Surface Preparation
2.1.1 New Surface
New surface
requires preparation such as removal of dust, dirt and foreign matter. In case
of cracks, voids & damages it should be repaired. The surface should be in just
wet condition, prior to putty application.
2.1.2 Very Smooth
Surface
If the surface
was made by Cement ghutai (smoothening) which normally is
very smooth, bonding with putty may not become sufficiently strong. Scraping
the surface with emery stone/paper is recommended before the skim coat application. The surface should be in just-wet condition, prior to putty application
2.2 Preparation
of Wall Putty Paste
- Mix Wall Putty slowly in @
35 - 40% water by volume to prepare a paste of desired consistency.
- Mix vigorously for 5-10
minutes for making lump-free and uniform paste.
·
Product
should be mixed in such quantities that it could be used within 2 hrs of its
preparation.
·
Mixing
could be done manually or by a suitable method.
2.3 Application
·
Ensure
that the surface is totally clean.
·
Ensure
that surface is moderately rough (neither too-rough nor too-smooth).
·
Ensure
that surface is just-wet. Over-wetting resulting in the accumulation of water on the surface should be avoided.
·
Apply
first coat
·
Use
spatula I blade I trowel on the wall with "bottom to
top" Configuration
- Apply second coat
preferably after @ 12 hrs application of 1 st coat
·
Re-mix
putty paste again for @ 1 minute if it is left undisturbed for @ 30 minutes.
·
Allow
complete drying @ 2 days and then use fine emery paper to remove the application
mark, if any or half an hour application of 2nd coat smoothening
could be done with a trowel.
·
After
application of second coat, wet surface twice a day for at least one day, if the season demands Water shall be applied gently.
- Filler Coat should be
apply after 3 or more days of Skim Coat of work for bonding between skim coat and paint.
·
Clean
application tools
2.4 Precaution
·
Use
rubber gloves while mixing.
- Precaution should be taken
to avoid dust inhalation while handling putty powder or during removal of application marks with fine emery paper say wearing nose mask.
·
Once
putty paste has hardened, it shall not be used by adding water.
2.5 Storage
- Store Hega Wall Putty in a dry place. Open the
bag just before used.
3.0 Option
2: Applying procedure for Apex Skim Coat
Apex skim Coat can be applied to all types of cement
plasters, ceilings, asbestos sheets, concrete, etc.
3.1
Surface Preparation
Ensure
that the surface to be painted is free from any loose paint, dust or grease.
All loosely adhering material of the wall and any previous grown fungus, algae
or moss need to be removed by wire brush, putty blade or emery stone. Surface
imperfections such as holes, dents, cracks can be filled using a mixture of
cement & fine sand (in the ratio of 1:3).
3.2 Mixing
Mix the Apex Skim
Coat powder with clean water in a clean non-absorbent vessel. Add water
gradually to the powder. Mix well by hand or mechanically for about five to ten
minutes till a uniform paste is formed. 20kg of Apex Skim Coat requires 7 -8
liters of water. Slow speed is recommended for mixing. Make sure the mixture is
lump-free.
3.3 Application
If the surface is the much drier or
high-temperature condition, dampen the surface with clean water. Allow excess
water to drain off, apply the mix on the surface to the desired thickness
(maximum of 2mm) from bottom to upward direction with the help of a steel trowel/putty blade. After drying of the first coat, rub the surface gently
with a wet sponge or putty blade in order to remove any loose particles. Apply
the second coat after the first coat has fully dried and set. Level the surface
with sandpaper (No. 220-320) to remove unevenness. Use sandpaper
vertically.
3.4 Precautions
During Application
-
Proper
mixing is very important and hence attention to be given for proper mixing in
order to get the best results.
-
Always
prepare a required quantity of skim coat and use it within 1.5 hours after the
mixing. If it is hard to apply, add some water. (Pot life of mixed material may
vary with different environmental conditions.)
-
Do
not over thin.
-
For
better finish, the thickness of each coat should not exceed 2mm and total
plaster thickness should not exceed 4mm.
-
Do
not apply when the ambient temperature is less than 5'C or if the temperature might
drop to this level within 4 hours after application.
-
Protect
from a high heat for 2-4 hours after applying.
-
Always
keep the partially used packs properly tied up without opening to the atmosphere.
During Usage
-
Though
it non-toxic product but avoid dust inhalation, direct eye, and mouth contact
and prolonged skin contact. In case of eye or mouth contact, flush with clean
water at least 15 minutes and seek medical help.
-
Avoid
spreading of powders when mixing and moving.
-
Being
white cement added product, people with allergy of cement should take proper
precautions.
Storage
Store in a dry place. Better to use within one year after
manufacturing.
5. Inspection for Construction
All kinds of inspection
for construction shall be carried out by the site Engineers along with
Engineers representative and QA/ QC Engineer of SANKEN as per the standards and
specifications.
However, prior
information shall be given to Consultant representative at the site to proceed
necessary checking’s periodically & make final comments.
Inspection shall be
carried out while progressing of the work & approval shall be granted
without affecting the progress of the work.
6. Safety Plan
Safety of the personnel and properties is to be given prime
importance and all the works to be carried out without causing any accidents or
property damages.
·
Adequate access and egress should be provided to
the site for work
·
All workers should wear basic personnel
protective equipment.
· All the equipment, tools being used for the work
should be in good working condition and maintained.
·
Adequate
illumination shall be provided during night time.
·
First aid facilities and vehicles for emergency
cases shall be available at the site.
Sure.
ReplyDelete