Wednesday, July 1, 2020

METHOD STATEMENT FOR GRANITE FLOOR AND GRANITE WALL TILING


Content

 


1.0           Introduction

2.1           Method of Granite Floor Tiling

2.2           Method of Granite Wall Tiling

3.0           Responsibilities

4.0           Quality Controlling & Quality Assurance

5.0           Safety


1.0 Introduction

This method statement gives a step by step procedure for Granite Tiling of Floors and Walls.

2.1  Method of Granite Floor Tiling.
  • The concrete slab surface on which the Granite are to be laid will be cleaned, wetted & mopped prior to commence the laying of Granite tiles.
  • Granite tiles will be matched & selected according to the approved Drawings.
  • Granite shall cut using diamond blade saw.
  • Before laying the Granite tiles, guiding lines (i.e. reference lines for positioning of tiles) has to be marked on concrete floor.
·         The final finish level less the thickness of the granite slab will determine the level of the mortar bed. 1:3 Cement Sand mortar will be spread over the prepared surface evenly as little more than required thickness to make bedding for Granite. The mortar will be consisting of minimum water content which necessary to achieve workability. 
·         A granite slab will be temporarily kept over the bedding and stamped well with a Wooden / Rubber Mallet to achieve the required finished level of the granite floor.
·         A spirit level will be used continuously to determine the horizontal level of each slab and to carry the level from slab to slab.
·         The temporary granite slab laid will be carefully removed from the bedding and      stacked.
  • Dry cement powder will be evenly spread on top of the stamped bed and clean water sprayed to wet the cement sand bed thoroughly.
  • The removed granite slab will be placed once again in the same position and stamped with a Wooden / Rubber Mallet to achieve the final finished level of the granite floor. If squeezed cement grout collected in the Granite tile groove will be removed & cleaned properly.
·         The newly laid floor will be protected from foot traffic for minimum 24 hours.
  • Grouting of joints will be done soon after. The grooves between Granite tiles then will be finished with the approved tile grout and entire surface will be cleaned with damped cloth before hardening any excess tile grout over the Granite surface. This method will be repeated until the entire floor is completed.
  • Cement mortar will be spread, tamped and leveled properly using Aluminum level bars reference to the level pegs on floor.
  • Over the wet cement mortar bedding cement will be spread just before placing the Granite tile.
  • The Granite tiles will be fixed over the bedding one after another according to the base tile lines, each tile will be gently tamped with rubber mallet.
  • Move the tile slightly in all directions to ensure the bond. Once it is satisfied with the bond, move the Granite tile to its final position. Repeat the process for each tile.
  • Tile grout will be properly mixed with water as per manufacturer’s instructions. The tile grouts will be spread over the surface with a grout float (i.e. Flexible Rubber Pad). During the application of grout, the grout float shall be held at a 45-degree angle to the floor or wall, pushing the grout securely into the gaps. Scrape the flat edge of the grout across the tile surfaces to remove residual grout and entire surface shall be cleaned off with damped cloth before hardening any excess tile grout over the Granite surface.

  • Leave the floor for 2-3 days to seal the grout with appropriate grout sealer as specified by the manufacture which shall resistant to water, oil and stains.
  • During the fixing of Granite tiles, a straight edge (normally 100mm x 25mm Aluminum hollow bar) shall be used to check the evenness of the tile surface and plumb bob shall be used to check the verticality.

2.2  Method of Granite Wall Tiling
·         The structure will be thoroughly cleaned.
·         Granite tiles will be matched & selected according to the approved Drawings.
·         The stainless steel 25mm wide strip (gauge 22) will be slide into the slit in the granite tile with Epoxy adhesive.
·         Surface alignment will be set out using Horizontal & Vertical strings at regular intervals. The top level of the bottom row of Granite tiles will be established by a string.
·         The Bottom row of tiles will be placed on the finish floor using 1 : 3 cement and sand mixture and compacted with a rubber hammer until the required level is reached.
·         The alignment will be checked by using a spirit level.
·         All necessary holes will be drilled into the concrete or brick walls/columns at pre-marked position to receive anchors and fix the strip to the concrete or brick walls/columns.
·         Approximately 12 hours after fixing of Granite tiles, space between Granite tile & structure will be back filled with a 1:3 Cement Sand mortar.
·         The next row will be placed and preceded with same process.
·         This procedure will be repeated until the whole cladding is completed.
·         During the fixing of Granite tiles, a straight edge (normally 100mm x 25mm Aluminum hollow bar) shall be used to check the evenness of the tile surface.
3.0 Responsibilities
             Position
                                   Responsibility
Engineer in charge
1.      Obtain approval for layout drawing and material related to tiling work.
2.      Provide all resources for Tiling Works.
3.      Controlling of Quality.
Assistant Engineer
  1. Assist to the Engineer in Charge.
  2. Keeping records of Tiling.
Construction Supervisor
1.      Assist to Assistant Engineer.
2.      Handling the Tiling gang.
Survey Helper
1.      Monitor and maintaining all survey works related to Tiling Works.
Safety Officer
  1. Monitor Safety and Health in the working area.


4.0  Quality Controlling & Quality Assurance
·         Experienced supervisory staff will be employed for inspecting the work.
·         Selected skilled workers will be engaged for Tiling work.
·         Vertical & horizontal Base tile lines marked on the tile bed.
·         Area of work in progress will be barricaded to avoid entering outsiders.

5.0  Safety

  • Working platforms with hand rails and cat walk ladders will be fixed to   access and work at higher levels.
·         Workers will be provided with safety helmets & hand gloves.
  • Safety belts will be provided for all employees who work at higher level flat forms.

No comments:

Post a Comment

METHOD STATEMENT FOR CHEMICAL ANCHORING REBAR WITH HILTI HIT-RE 500 V3

  1.0               INTRODUCTION   1.1    Name of the project              : Proposed Car Park and Mixed development Project 1.2    ...