1. Introduction
This
method statement specifies the sequence and methodology to be followed for plastering
of Surfaces of brick walls, concrete columns and concrete walls.
2. References
Structural
Construction Drawings
Approved Shop
Drawings
Project
Specification
3. Material
3.1 Cement
3.2 Sand
3.3 Approved
Adhesive
4. Method of plastering
- Wall surface shall be
properly cleaned before applying plaster.
- All the projections
more than 5mm from the general face of the wall shall be removed to get a
uniform surface and to reduce the amount of plaster.
- To get good key of
the plaster with wall surface, the mortar joints in the brick masonry shall
be raked out to a depth of 13 to 20 mm
- The joints and the
surfaces shall be cleaned with hard wire brush to remove loose mortar and
dust.
- Level pegs on walls shall
be fixed with reference to the off lines to brick walls set out in floors. (Using center plumb bob and
nylon thread).
- All the brick walls shall be watered
before pasting mortar on walls.
- For maintaining uniform thickness of
plaster, screeds shall be formed on the wall surface by fixing dots.
- All the embedded service lines and
provisions (Conduits, Boxes and etc. xc) shall be completed on brick
walls and check with the MEP drawings.
- Apply the plaster to required
thickness as specified in drawings
- External Plaster
shall be 15mm thick to wall in cement and sand 1:3 with adding approved
adhesive finished semi rough with wooden float.
- Internal Plaster Shall be 15mm thick to wall in cement
and sand 1:4 with adding approved adhesive finished semi rough with
wooden float
5. Curing
Curing shall be carried out 24 hours
after applying the cement plaster.
6. Inspection for Construction
All kinds of inspection for
construction shall be carried out by the site Engineers along with Engineers
representative and QA/ QC Engineer of SANKEN as per the standards and
specifications.
However, prior information shall be
given to Consultant representative at site to proceed necessary checking’s
periodically & make final comments.
Inspection shall be carried out while
progressing of the work & approval shall be granted without affecting to
the progress of the work.