Saturday, January 4, 2020

METHOD STATEMENT FOR SLAB AND COLUMNS FORM WORK

                                                                                                     
1.0       INTRODUCTION
WPC Office complex is a sixteen storied building with a total floor area of  about 40,000 sqm  including the basement parking area, twelve  office floors and council chamber on the 13th floor level   
 As per the architectural design, structural elements are slightly different than the each and other floors to facilitate the different types of MEP services as required for the floor arrangements. Therefore, we use a conventional formwork system with necessary modifications as required at the different floor levels.   

2.0       REFERENCES
  • Structural Construction Drawings
  • Inspection sheet for structural work
  • Form work method statement
  • Trial Mix Reports/ Admixture Reports

3.0       RESOURCES

3.1. Material
1.   Timber – 50 x 50 , 100 x 100 mm
2.   15 mm thick. Plywood sheets
3.   Form ties and pre cones
4.   GI Pipes / acro jacks – For support
5.   Ordinary Portland Cement
6.   Aggregates
7.   Sand
8.   Water
9.   Admixtures
10.        Water Bars
11.        Ready-mix Concrete ( as per approved mix design )
The mix proportions are designed by mix design and verified by Trial mix and trial workability tests.




1.    Batching plants
2.   Truck Mixers
3.   Stationary Concrete Pump with Lines/ Pump Cars
4.   Concrete Distributor
5.   Shovel/Mammoth
6.   Porker/Shutter Vibrator
7.   Level Bar
8.   Level Machine with  staff
9.   Concrete Chute
10.        Tower Crane with Bucket
11.        Mason Trowel
12.        Wooden Float
13.        Plumb bob
14.        Water pressure gun m/c
15.        wire brush
16.        Compressor



3.3. Man Power
1.  In charge Engineer (Structural) – 01 no
2. Concrete In-charge  Engineer – 01 no
3. Assistant Engineer – 02 nos
4. Construction Supervisor – 01 no
5. Survey Helper- 01 no
6. Concrete Forman – 01 no
7. Masons – according to the requirement at that time
8. Skilled Workers - according to the requirement at that time
9. Unskilled Workers- according to the requirement at that time
10. Standby Carpenter - according to the requirement on that time
11. Standby MEP Service Workers -according to the requirement on that time
12. Machine Operators - according to the requirement at that time
13 .QA/QC Engineer – 01 no
                                                                            

4.0 Form Work


This is a major activity that bears the weight of concrete until it gets the required strength. So it is essential to take care of the correct methodology for fixing and supporting.

4.1 Type of formwork


·         Sides of Beams and columns    
·         Soffit of slab and beams
·         Stair case formwork

4.2. Formwork Arrangement –Columns and Slabs   

 4.2.1 Formwork Arrangement – Columns

  • Plywood (15mm thick) will be used for smooth finishing surfaces
  • Formwork arrangement for columns is shown in drawing no. 1
  • Setting out carry out according to approved structural or setting out drawing.
  • Verticality of the column formwork will be checked using four plumbs at two nos. on each surface.
  • 200 mm off lines are marked on floor concrete to check the position of the column.

 4.2. 2 Formwork Arrangement – slab and beams

  • Plywood sheets (15mm thick) will be used for smooth finishing surfaces.
  • Plywood sheets shall be laid on GI pipes (distance between two pipes 200 mm), which are on the 4”x4” timber blocks, with a distance of 600mm.
  • Beam soffit will be supported by acro jacks
  • Slab soffit will be supported with acro jacks by using 4”x 4” timber planks and U jacks.
  • Beam bottoms shall be supported on pipe supports and T – jacks, which are held on the below slab.
  • All joints will be covered with appropriate sticking tapes
  • Mineral mold the oil will be applied  before concreting
  • Formwork arrangement for slab and beams are shown in drawing no. 2
  • Before doing the concrete,  the slab shall be leveled with the leveling instruments

      

4.3 Construction Joints

Slab and beams may be temporally stopped keeping continuation further and called construction joint. The way is to depend upon structural definition keys will be provided as required on specifications shown in the sketch. Beam vertical construction joint keeps 1/3 or 2/3 of concrete beam span. As the Structure is divided into zones, construction joints shall be formed, when doing part concreting. Details of the typical construction joints for a slab are shown in Fig 4.

Stair Case Formwork (Conventional Formwork)

Staircase formwork shall be carried out in the same way of doing horizontal formwork. Arrangement of a slopping formwork is shown in below Fig. 3
Note: Staircase concreting will be done only after completion of the slab concrete. (i.e. starting floor & the landing floor within one-floor height)


4.4 Cleaning of formwork

  • Surfaces will be well cleaned of all dirt and dust by using  compressor or water pressure m/c

4.5 Removal of Formwork


All formwork should be removed without damage on concrete. The form of supports would not be struck until the concrete has reached the sufficient strength. Form work may be removed after the time as shown in the following,

Form work removing done according to Table 2.2 in specification if we concrete without admixtures or refer table 5.3 at ICTAD Building works volume 1.

4.6 Stacking of removed formwork

  • Removed panels will be stored at safe covered place
  • All panels will be installed vertically

4.8 Check List

  • Marking lines
  • Alignment of vertical form work
  • Levels of horizontal formwork
  • Supports
  • Dimensions
  • Joints of panels
  • Cleaning of form work

4.9 Quality Controlled measures

4.9.1 Column form work

Surveyor helper marked setting out lines on slab. Before erect column form work marking lines are check by Engineer or related officer. After erecting the column form works again verticality check. After complete the concrete pouring supervisor will be check verticality of form work and cleaning of surround area.

  

5.0 Re bar Work


  • Mill reports and test reports for steel will be submitted to the consultant before execution of work
  • Re bar schedules will be prepared by an Engineer  
  • Cutting and bending will be done at site or bar bending yard accordingly bar schedule.
  • All laps, joints and anchorage will be kept to the standard given in drawing by consultant

5.1 Equipment’s

  • Bar bending machine
  • Bar cutting machine
  • Chop saw m/c

5.2 Reinforcement steel placing

  • All steel bars will be cleaned before placing
  • Cover blocks will be used to maintain the adequate cover to reinforcement
  • Chairs or Stools will be used to maintain the gap between top and bottom bars

5.3 Cover to reinforcement
          Cover to reinforcement will be follow as per structural drawing and related site instructions.

Minimum lap length as specified by consultant


5.5 Check List of Re bar

  • Steel sizes, spacing and position
  • Steel tying and binding
  • Lap length, anchorage length
  • Covering
  • Chairs or stools between top and bottom net
  • Cleanliness,


If any MEP work related to pile cap, place and confirm prior to concrete works.


6.0 CONCRETE WORK

6.1 Materials
  • All concrete grades will be used as specified in drawings and Consultants

6.2 Concrete Used
  • Site Mixed ( get prior approval from Consultant )
Using concrete mixtures done by manually at site for G15  
  • Batching Plant Mixed
Concrete batching plants Mix Designs approval gets from consultant


6.3 Transportation of concrete
  • Concrete will be transported to the site by truck mixers from batching plant
  • Site mixed concrete done by at site for G15 ( using gage boxes and necessary inspection to check quality )

6.4 Placement of Concrete

  • Consultant will be informed at least 12 hours before approval required
  • If needed we used a pump car or Tower crane to pump concrete.
  • As level increases, permanent pipe lines will be installed to pump concrete
  • After the approval of consultant for reinforcement and form work, concreting will be done with all necessary equipment
  •  Chute will be used where required keeping slopes not to cause segregation
  • Poker vibrators shall be used to compact the concrete well


6.5 Leveling of Concrete
  • Height gauges will be used to maintain the correct levels
  • Concrete finish level will be marked at Column reinforcement to control the pouring on pile caps
  • Concrete finish level will be checked after concreting using leveling instrument
  • If necessary string is used to checked level of concrete

6.6 Pile Cap Concreting
  • Dust and debris, which exist inside the formwork, shall be blowered and cleaned well, prior to commence the concreting. Cavities if there are any, shall be sealed to avoid grout leakages. Pile cap shall be concreted by using the mobile or stationery concrete pump and distributors. Concrete shall be poured in to the pile cap.
  • Proper compaction shall be done by using poker vibrators. Level of the pile cap and the surface finish shall be maintained while doing the concreting. A careful attention shall be paid to ensure whether the conduits and other service lines are not damaged (if embedded); and if there are damages in service lines, it shall be informed to the relevant sub-contractor. If somewhere concrete not segregation in significant that concrete part remove .

6.7       Large scaled Pile Cap Concreting
The large scaled element, which the depth is higher than 1000mm,shall be concreted strip wise, as shown in the follow  and the thickness of concrete layers shall not be exceeded 1000mm. By doing this way, it can be laid the concrete, over the previously concreted layer before it is getting set.

                                   

   6.8 Compaction of concrete


After pouring one layer, the compaction of about 25sec to 30sec, shall be done by inserting vibrator based on the marks. The vibrator needle should not disturb previously concreted layers. Vibrator inserted in 1m intervals of above intervals .



6.9       Testing related to the Concrete work


  • Slump will be checked for each truck mixer and record with consultant representative
  • 150mmx150mmx150mm test cubes will be produced for compressive strength checks for 7 days and 28 days
  • Test cubes will be checked in NBRO or related Lab  



6.10 Curing of concrete

  • Curing shall be started as soon as possible and practical after placement of concrete
  • The concrete shall be covered with a layer of sand  and kept constantly wet for a period of 7 days


6.11 Green Removing

Removing of the grout, wire brushing of the construction joints or cleaning with water pressure gun shall be carried out within the concrete is in the fresh state.




6.13 Check List


  • Form work
  • Reinforcement
  • Supports
  • Manpower
  • Machinery and equipment arrangement
  • Sample testing





7.0. RESPONSIBILITIES

Position
Responsibility
 Engineer in charge (structural)
1.   Get approved for Concreting (i.e. for  R/F, F/W and for Services)
2.   Cleaning of debris in the form work.
3.   Sealing the joints of formwork to avoid the grout leaks.
4.   Arranging all infrastructures for Concreting.
5.   Curing of Concreted elements.
Concrete In charge Engineer
1.   Estimating the required Concrete volume and order from the batching plant.
2.   Testing and Sampling the Concrete.
3.   Keeping records of concreting.
4.   Handling the traffic of the Concrete truck mixers.
5.   Quality controlling of Concreting.
Assistant Engineer
Assist to the Tower Incharge.
Construction Supervisor
1.   Assist to the Concrete Incharge.
2.   Handling the Concrete gang.
Concrete Forman
Handling the Concrete gang.
Survey Helper
Maintaining the verticality and required levels of the concrete elements.
Admin Officer
Providing the welfare facilities for Concreting staff and for workers.
Safety Officer
Marinating Safety and Health in the working area.


9.0     SITE ARRANGEMENT

Site Infrastructure Arrangement plan is attached as annexure.

10.0                 SAFETY  PLAN

·         All the dangerous areas must be barricaded
·         Safe flat forms for working at higher levels shall be provided.
·         Safety Guard rails shall be provided at the perimeter run.
·         All the electrical wires and sockets such a way that must be covered to safety regulations
·         Very good site illumination will be provided, if concrete pouring continues to the night time.     
·         Water pumps must be ready at any time for immediate use.
·         First aid facilities and vehicles for emergency cases shall be available at site.
Refer the Sanken Lanka Safety Manual for other safety precaution and regulations

No comments:

Post a Comment

METHOD STATEMENT FOR CHEMICAL ANCHORING REBAR WITH HILTI HIT-RE 500 V3

  1.0               INTRODUCTION   1.1    Name of the project              : Proposed Car Park and Mixed development Project 1.2    ...